Well the first stage of putting up the Reward ICF system is on it's way. Over the coming weeks the concrete will be poured to bring the walls up to the first floor. Then end of Stage 1 - should be completed by mid-late June.
Stage 2 looks like it will complete August timeframe as this will incorporate installing the concrete floors (July) , putting up the next floor ICF system, pouring the concrete in these walls by end of July. Following on from this will be laying all the floors and ensuring all the pipes are installed for the heating/plumping etc on both floors. All should be completed by August.
As you can see from the pictures not all the windows are cut out as yet. Can't wait for this floor to be completed.
And the next stage!!
Then in August we can get the windows measured up!!!! Yipee!!!