Friday, June 25, 2010

External Ground works


Arrived on site yesterday but no radiators or piping had arrived for the plumbing to start work!! This will definitely delay the move in time as we can't start the flooring without the plumbing work being completed!!

Tiles for the downstairs are on order and being delivered next week so will have to delay the tiler and the Kitchen installation :-(((
May not be in the house now before I head back to work from my Maternity Leave.

On the plus side the external ground work has being going on - all drains around the house have been put in, hardcore laid out and getting ready to put in the footpaths around the house :-).
The Bio Cycle unit has arrived which hopefully will be installed over the next few days.

Below are the latest pics.