Items Completed:
Site breakthrough and set up for build start
Build Stage 1-3 paid for and completed.
Build Stage 4 completed and stage 5 underway
Tiles selected and ordered for downstairs Kitchen/dining/hallway/utility
Wooden floor selected, paid & ordered - walnut - for downstairs seperate living room
Wooden floor selected, paid & ordered - birch - for all rooms & landing upstairs (except bathrooms)
ESB connection applied for; and paid for as was approved connection.
Kitchen selected and finalised
Double bed & bedside lockers for master bedroom
Shower tray & glass wall selected and ordered for the ensuite
Main Bath selected - NICE !!!
All sinks, loos, taps etc selected, paid for and ordered
Bought a sofa & 2 chairs about 6/7 years ago; in sis's house so will have to move them into my place
Got a free second table & chairs which will most certainly do till we need buy one when we have money!!!
Items to be Done:
Tiler selected and booked to complete the downstairs tiling before Kitchen is fitted
Wood floors to be laid ... aaaaggghhh ... the cost of it all!!!
The bathroom & ensuite tiles to be selected
Chippy in to create the surround for the bath which is to be tiled.....
Kitchen cooker, extractor hood & fridge freezer date for delivery to be finalised
Washing machine and dryer to be selected & ordered
Plumbing of wood stove, buffer tank, HRV & Solar panel to be organised ... must contact builder on best time for this in the schedule???
Double check on the extractor fan hole in the wall with the builder??
Get the stove flues quote and finalisation of dates to be installed with kiely stoves
Eircom for telephone connection
County council for water connection (who are on 'work to rule' and can't get through to them via phone and pretty stuck due to caring for baby too!!)
Once electric cert completed get ESB in for Electricity connection
Pay for the kitchen due to be paid next week!!
Pay the Stage 4 to the builder due end of this week !! (stage 4 of 5 stages)
Pay tiler and for wood floor to be layed aaaaghhhhh
Covering the concrete stairs .... with what & How?
Outside light fittings, internal light fittings!!!
Bar stools for the kitchen island unit
..........I know there is more to be added to the list but my head is now fried!!!
Subscribe to:
Post Comments (Atom)
2 comments:
Hi guys,
Love the blog...
As I built Fitzgerald Construction Website and also promoting the company on facebook (http://www.facebook.com/pages/Fitzgerald-Construction-Ltd/194277973933481?sk=wall) I was wondering if there will be any updates etc?
Have a nice day!
Anna
Hi Anna,
for some strange reason google locked us out of the blog and we were no longer able to get back to update it!
I've tried everything but no joy with any contact I made to them.
Ask Kieran for my email address and I'd be happy to let you know the updates and anything else you need to know.
Cheers,
Tanya
Post a Comment